Page 3 - Chapter 1 General Information; Safety; Do not work alone under hazardous conditions.; Batteries must be recycled.; Deliver the battery to an appropriate recycling
1 Chapter 1 General Information The CTEP/G Series Enclosures provide power sourcing for broadband cable operations. Safety This Safety Guide contains important instructions that should be followed during installation and maintenance of the APC equipment and batteries. It is intended for APC customer...
Page 4 - Chapter 2 Installation; Specifications; Models Supported; Model Number
2 Chapter 2 Installation Prior to installing the power supply enclosure, a utility breaker box must be installed on the pole. Utility line voltage must be routed to the enclosure. Local, state, federal and/or National Electric Code (NEC) regulations regarding location, permits and electrical wiring ...
Page 5 - Environmental Specifications; Operating Temperature; Physical Specifications; Characteristic Specification
3 Specifications Environmental Specifications Operating Temperature -40º F to140º F (-40º C to 60º C) Humidity 5% to 95% noncondensing within enclosure Physical Specifications Characteristic Specification Height X Width X Depth CTEP0 CTEP3 CTEP4 CTEP6 CTEP8 14” x 24” x 16” (36 x 61 x 41 cm) 30” x 24...
Page 6 - Installing the Enclosure; Models may vary in appearance from those depicted below.; Install the Mounting Bracket on a Pole
4 Installing the Enclosure Models may vary in appearance from those depicted below. Install the Mounting Bracket on a Pole CTEP0/CTEP4 models CTEP3/CTEP6/CTEP8 models Install the Enclosure on the Mounting Bracket CTEP0/CTEP4 models Secure the bolts, nuts, and washers on the mounted bracket prior to ...
Page 7 - Ground Mount Installation
5 Ground Mount Installation 1. Install an APC approved concrete pad. Contact your dealer or refer to the APC Web site, www.apc.com for more information. 2. Secure the enclosure to the pad. Refer to the diagrams below. 0 Battery Enclosure: Attach the ground skirt to the concrete pad. Attach the enclo...
Page 8 - Wiring; Grounding
6 Wiring Grounding 1. Install and interconnect ground rods appropriate for proper grounding according to local electrical code requirements. 2. Route ground wires from the ground system into the bus bar located on the enclosure. Connecting Utility Power to the Enclosure CTEP/G3 (CTEP/G6&CTEP8 ha...
Page 9 - Options; For available options see your dealer or the APC Web site,; Connecting the Batteries; Tape one end of each jumper cable prior to installation.; Bottom Shelf
7 Options An optional External AC Generator Interface is available for the following models: CTEP3-120GI; CTEP4-120/240GI; CTEP/G6-120GI; CTEP8-120/240GI For available options see your dealer or the APC Web site, www.apc.com . Connecting the Batteries The battery circuit breaker must OFF prior to ba...
Page 13 - Chapter 3 Service, Contact and Warranty Information; Service; Support
11 Chapter 3 Service, Contact and Warranty Information Service APC makes every effort to ensure parts and equipment arrive in working condition. Occasionally, it may be necessary to return parts or equipment that are not in working condition. If the UPS requires service do not return it to the deale...