- Page 2 – SAFETY CONSIDERATIONS; WARNING
- Page 9 – INSTALLATION; Jobsite Survey; Step 1 — Plan for Unit Location; NOTE
- Page 13 – Roof Curb Mount —; Ductwork must be attached to curb and
- Page 14 – Step 5 — Field Fabricate Ductwork; Do not connect ductwork to unit.; For Units with Accessory Electric Heaters —; Step 6 — Rig and Place Unit; UNIT DAMAGE HAZARD; CAUTION; Positioning on Curb —
- Page 15 – DETAIL A; Step 7 — Horizontal Duct Connection
- Page 16 – To remove the hood parts package:
- Page 17 – Step 9 — Check Pulley Alignment and Belt Tension; Pulley Alignment —
- Page 18 – All units must have an external trap for condensate; Step 11 — Make Electrical Connections; ELECTRICAL SHOCK HAZARD; Do not use gas piping as an electrical ground.; DETAIL
- Page 19 – FIRE HAZARD; Units Without Factory--Installed Disconnect —; TB; Units Without Disconnect Option; Table 2 – American/European Wire Conversions
- Page 20 – Central; Failure to follow this caution may cause a short circuit.
- Page 21 – Heat Anticipator Settings —; Electric Heaters
- Page 22 – PremierLink
- Page 24 – Field Connections; Table 3 – PremierLink Sensor Usage
- Page 26 – Space Sensors —; Connect Thermostat —
- Page 27 – Economizer Controls; COVER REMOVED
- Page 29 – CCN Bus
- Page 30 – RTU Open Control System
- Page 32 – Table 8 – RTU Open Controller Inputs and Outputs
- Page 33 – Indoor Air Quality (CO
- Page 35 – RTU Open Controller Integration Guide; SW3 Protocol Selection; Baud Rate Selections
- Page 36 – Cable; Handheld Connections
- Page 37 – Table 9 – LEDs; Run; RTU Open; Outdoor Air Enthalpy Control; Differential Enthalpy Control —
- Page 38 – Wiring; Smoke Detectors; Return Air Sensor Tube Installation –
- Page 40 – Table 10 – Unit Wire/Fuse or HACR Breaker Sizing Data; : See page 41 for table legend and notes.
- Page 41 – Legend and Notes for Table 10
- Page 42 – IV Wiring; Step 12 — Adjust Factory--Installed Options; EconoMi$er IV Occupancy Switch —; Step 13 — Install Accessories
- Page 43 – PRELIMINARY INFORMATION; ELECTRICAL
50TC --- D
Single Package Rooftop, 50Hz
Cooling Only
with Puron
r
(R --- 410A) Refrigerant
Sizes: 17, 20, 24, 28, 30
Installation Instructions
NOTE
: Read the entire instruction manual before starting
the installation
TABLE OF CONTENTS
SAFETY CONSIDERATIONS
2
. . . . . . . . . . . . . . . . . . . .
INSTALLATION
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Jobsite Survey
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Step 1 -- Plan for Unit Location
9
. . . . . . . . . . . . . . . . . .
Roof Mount
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Step 2 -- Plan for Sequence of Unit Installation
13
. . . . .
Curb--Mount Installation
13
. . . . . . . . . . . . . . . . . . . .
Pad--Mount Installation
13
. . . . . . . . . . . . . . . . . . . . .
Frame--Mount Installation
13
. . . . . . . . . . . . . . . . . . .
Step 3 -- Inspect Unit
13
. . . . . . . . . . . . . . . . . . . . . . . . . .
Step 4 -- Provide Unit Support
13
. . . . . . . . . . . . . . . . . .
Roof Curb Mount
13
. . . . . . . . . . . . . . . . . . . . . . . . .
Slab Mount (Horizontal Units Only)
13
. . . . . . . . . .
Alternate Unit Support
(In Lieu of Curb or Slab Mount)
13
. . . . . . . . . . . . .
Step 5 -- Field Fabricate Ductwork
14
. . . . . . . . . . . . . . .
For Units with Accessory Electric Heaters
14
. . . . .
Step 6 -- Rig and Place Unit
14
. . . . . . . . . . . . . . . . . . . .
Positioning on Curb
14
. . . . . . . . . . . . . . . . . . . . . . .
Step 7 -- Horizontal Duct Connection
15
. . . . . . . . . . . .
Step 8 -- Install Outside Air Hood — Factory Option
16
. .
Step 9 -- Check Pulley Alignment and Belt Tension
17
. . .
Pulley Alignment
17
. . . . . . . . . . . . . . . . . . . . . . . . .
Belt Tension
17
. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Step 10 -- Install External Condensate Trap and Line
18
. .
Step 11 -- Make Electrical Connections
18
. . . . . . . . . . .
Units without Factory--Installed Disconnect
19
. . . .
Units with Factory--Installed Disconnect
19
. . . . . . .
All Units
19
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Factory--Option Thru--Base Connections
20
. . . . . .
Units without Thru--Base Connections
20
. . . . . . . . .
Field Control Wiring
20
. . . . . . . . . . . . . . . . . . . . . . .
Thermostat
20
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Unit without Thru--Base Connection Kit
20
. . . . . . .
Heat Anticipator Settings
21
. . . . . . . . . . . . . . . . . . .
Electric Heaters
21
. . . . . . . . . . . . . . . . . . . . . . . . . . . .
Low--Voltage Control Connections
21
. . . . . . . . . . . .
PremierLink
t
(Factory Option)
22
. . . . . . . . . . . . . . .
Supply Air Temperature (SAT) Sensor
24
. . . . . . . . .
Outdoor Air Temperature (OAT) Sensor
24
. . . . . . .
EconoMi$er2
24
. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Field Connections
24
. . . . . . . . . . . . . . . . . . . . . . . . . .
Space Sensors
26
. . . . . . . . . . . . . . . . . . . . . . . . . . . .
Connect Thermostat
26
. . . . . . . . . . . . . . . . . . . . . . .
Configure the Unit for Thermostat Mode
26
. . . . . .
Economizer Controls
27
. . . . . . . . . . . . . . . . . . . . . . . .
Indoor Air Quality (CO
2
) Sensor
27
. . . . . . . . . . . . .
Outdoor Air Quality Sensor
27
. . . . . . . . . . . . . . . . .
Smoke Detector/Fire Shutdown (FSD)
28
. . . . . . . . .
Filter Status Switch
28
. . . . . . . . . . . . . . . . . . . . . . . .
Supply Fan Status Switch
28
. . . . . . . . . . . . . . . . . . .
Remote Occupied Switch
28
. . . . . . . . . . . . . . . . . . .
Power Exhaust (output)
28
. . . . . . . . . . . . . . . . . . . . .
Space Relative Humidity Sensor
29
. . . . . . . . . . . . .
CCN Communication Bus
29
. . . . . . . . . . . . . . . . . .
RTU Open Control System
30
. . . . . . . . . . . . . . . . . . .
Supply Air Temperature (SAT) Sensor
32
. . . . . . . . .
Outdoor Air Temperature (OAT) Sensor
32
. . . . . . .
EconoMi$er2
32
. . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Field Connections
33
. . . . . . . . . . . . . . . . . . . . . . . . . .
Space Temperature (SPT) Sensors
33
. . . . . . . . . . . .
Indoor Air Quality (CO
2
) Sensor
33
. . . . . . . . . . . . .
Outdoor Air Quality Sensor
34
. . . . . . . . . . . . . . . . .
Connecting Discrete Inputs
34
. . . . . . . . . . . . . . . . . .
"Loading the manual" means you need to wait until the file loads and becomes available for online reading. Some manuals are very large, and the time they take to appear depends on your internet speed.
Other Manuals for Carrier 50TC
Summary
50TC -- D 2 Communication Wiring -- Protocols 35 . . . . . . . . . . . . General 35 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Local Access 36 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . RTU Open Troubleshooting 36 . . . . . . . . . . . . . . . . . Outdoor Air En...
50TC -- D 9 INSTALLATION Jobsite Survey Complete the following checks before installation. 1. Consult local building codes or the U.S.A. National Electrical Code (Ref: ANSI/NFPA 70, [American Na- tional Standards Institute/National Fire Protection As- sociation], latest revision) for special install...
50TC -- D 13 Step 2 — Plan for Sequence of Unit Installation The support method used for this unit will dictate different sequences for the steps of unit installation. For example, on curb--mounted units, some accessories must be installed on the unit before the unit is placed on the curb. Review th...