Page 2 - NOTICE; Contents
February 2015 2 Quick Start Guide NOTICE This guide provides basic guidelines for Rosemount 3051 Transmitters. It does not provide instructions for configuration, diagnostics, maintenance, service, troubleshooting, Explosion-proof, Flameproof, or intrinsically safe (I.S.) installations. Refer to the...
Page 3 - System readiness; Confirm HART Revision capability; ) is loaded on your systems to ensure; Rosemount 3051 device revisions and drivers; Table 1; Table 1. Rosemount 3051 Device Revisions and Files
Quick Start Guide 3 February 2015 System readiness Confirm HART Revision capability If using HART based control or asset management systems, please confirm the HART capability of those systems prior to transmitter installation. Not all systems are capable of communicating with HART Revision 7 prot...
Page 4 - Transmitter installation; Step 1: Mount the transmitter; Liquid applications
February 2015 4 Quick Start Guide Transmitter installation Step 1: Mount the transmitter Liquid applications Coplanar In-line 1. Place taps to the side of the line. 2. Mount beside or below the taps. 3. Mount the transmitter so that the drain/vent valves are oriented upward. Gas applications 1. Plac...
Page 5 - Figure 1. Panel and Pipe Mounting
Quick Start Guide 5 February 2015 Figure 1. Panel and Pipe Mounting Panel mount (1) 1. 1. 5 / 16 ⫻ 1 1 / 2 Panel Bolts are customer supplied. Pipe mount Coplanar flange Traditional flange Rosemount 3051T
Page 6 - Bolting considerations; Figure 2 on page 6; Figure 2. Common Transmitter Assemblies; Table 2 on page 7
February 2015 6 Quick Start Guide Bolting considerations If the transmitter installation requires assembly of the process flanges, manifolds, or flange adapters, follow the assembly guidelines to ensure a tight seal for optimal performance characteristics of the transmitters. Use only bolts supplied...
Page 7 - In-line gage transmitter orientation; Figure 3; Figure 3. In-line Gage Low Side Pressure Port
Quick Start Guide 7 February 2015 In-line gage transmitter orientation The low side pressure port (atmospheric reference) on the in-line gage transmitter is located in the neck of the transmitter, behind the housing. The vent path is 360° around the transmitter between the housing and sensor. (See F...
Page 8 - Step 2: Consider housing rotation; Please note that over rotating can damage the transmitter.; Figure 4. Transmitter Housing Set Screw; Step 3: Set the switches; Figure 5
February 2015 8 Quick Start Guide Step 2: Consider housing rotation To improve field access to wiring or to better view the optional LCD display:1. Loosen the housing rotation set screw using a 5/64-in. hex wrench. 2. Turn the housing left or right maximum up to 180° from its original position (1) ....
Page 9 - Figure 5. Transmitter Electronics Board; Step 4: Connect the wiring and power up; lead to the “–” terminal.
Quick Start Guide 9 February 2015 Figure 5. Transmitter Electronics Board A. AlarmB. Security Step 4: Connect the wiring and power up Figure 6. Transmitter Wiring Diagrams (4–20 mA) A. 24 Vdc supplyB. R L ≥ 250 C. Current Meter (Optional) Shielded twisted pair cable should be used for best results. ...
Page 10 - Grounding for transient terminal block; Connect the wiring and power up
February 2015 10 Quick Start Guide 3. Ground housing to fulfill local grounding regulations. 4. Ensure proper grounding. It is important that the instrument cable shield: a. Be trimmed close and insulated from touching the transmitter housingb. Be connected to the next shield if cable is routed thro...
Page 11 - Step 5: Verify configuration; Device; Verifying configuration with a Field Communicator; configuration. Fast Key sequences for the latest DD are shown in; Note; Verify device configuration using the fast key sequences in
Quick Start Guide 11 February 2015 Step 5: Verify configuration Verify the configuration using any HART capable configuration tool or Local Operator Interface (LOI) - option code M4. Configuration instructions for a Field Communicator and LOI are included in this step. See Rosemount 3051 reference m...
Page 12 - Verifying configuration with Local Operator Interface (LOI); Table 4; Figure 8. Internal and External LOI Buttons
February 2015 12 Quick Start Guide Verifying configuration with Local Operator Interface (LOI) The optional LOI can be used for commissioning the device. The LOI is a two button design with internal and external buttons. The internal buttons are located on the display of the transmitter, while the e...
Page 13 - Switch HART revision mode; Table 4. LOI Button Operation
Quick Start Guide 13 February 2015 Note See Figure 10 on page 15 to confirm External Button Functionality. Figure 9. LOI Menu Switch HART revision mode If the HART configuration tool is not capable of communicating with HART Revision 7, the 3051 will load a generic menu with limited capability. The ...
Page 14 - Step 6: Trim the transmitter; a. Analog Zero Trim – Sets the analog output to 4 mA.; Example; Trimming with a Field Communicator; “Connect the wiring and power up” on; Table 5. Zero Trim Fast Keys
February 2015 14 Quick Start Guide Step 6: Trim the transmitter Devices are calibrated by the factory. Once installed, it is recommended to perform a zero trim on gage and differential pressure transmitters to eliminate error due to mounting position or static pressure effects. A zero trim can be pe...
Page 15 - Trimming with configuration buttons; configuration buttons located under the top tag.; Figure 10. External Configuration Buttons; Use the following procedures to perform a Zero Trim:; Perform trim with analog zero and span (option D4)
Quick Start Guide 15 February 2015 Trimming with configuration buttons A zero trim is to be performed using one of the three possible sets of external configuration buttons located under the top tag. To access the configuration buttons, loosen the screw and slide the tag on the top of the transmitte...
Page 16 - Safety instrumented systems installation; installation procedure and system requirements.
February 2015 16 Quick Start Guide Safety instrumented systems installation For Safety Certified installations, refer to product manual (00809-0100-4007) for installation procedure and system requirements.
Page 17 - Product Certifications; European Directive Information; North America
Quick Start Guide 17 February 2015 Product Certifications European Directive Information A copy of the EC Declaration of Conformity can be found at the end of the Quick Start Guide. The most recent revision of the EC Declaration of Conformity can be found at www.rosemount.com. Ordinary Location Cert...
Page 18 - Europe; Table 6. Process Temperature
February 2015 18 Quick Start Guide Europe E8 ATEX Flameproof and Dust Certificate: KEMA00ATEX2013X; Baseefa11ATEX0275XStandards: EN60079-0:2012, EN60079-1:2007, EN60079-26:2007, EN60079-31:2009 Markings: II 1/2 G Ex d IIC T6/T5 Ga/Gb, T6(-50 °C ≤ T a ≤ +65 °C), T5(-50 °C ≤ T a ≤ +80 °C); II 1 D Ex t...
Page 19 - International; Table 8. Process Temperature
Quick Start Guide 19 February 2015 N1 ATEX Type n and DustCertificate: BAS00ATEX3105X; Baseefa11ATEX0275XStandards: EN60079-0:2012, EN60079-15:2010, EN60079-31:2009Markings: II 3 G Ex nA IIC T5 Gc (–40 °C ≤ T a ≤ +70 °C); II 1 D Ex ta IIIC T95 °C T 500 105 °C Da (-20 °C ≤ T a ≤ +85 °C) Special Condi...
Page 20 - Brazil; Table 10. Input Parameters
February 2015 20 Quick Start Guide Special Conditions for Safe Use (X): 1. If the apparatus is fitted with optional 90 V transient suppressor, it is not capable of withstanding the 500 V insulation test required by IEC60079-11. This must be taken into account when installing the apparatus. 2. The en...
Page 21 - China; Table 11. Input Parameters
Quick Start Guide 21 February 2015 2. In case of repair, contact the manufacturer for information on the dimensions of the flameproof joints. 3. The capacitance of the wrap around label, being 1.6 nF, exceeds the limit in Table 9 of ABNT NBR IEC 60079-0. The user shall determine suitability for the ...
Page 22 - Japan; Combinations; Conduit Plugs and Adapters; Table 12. Conduit Plug Thread Sizes
February 2015 22 Quick Start Guide Japan E4 Japan Flameproof Certificate: TC20577, TC20578, TC20583, TC20584 Markings: Ex d IIC T5 Technical Regulations Customs Union (EAC) EM EAC Flameproof Certificate: RU C-US.Gb05.B.00400 Markings: Ga/Gb Ex d IIC T5/T6 X, T5(-60 °C ≤ T a ≤ +80 °C), T6(-60 °C ≤ T ...
Page 23 - Additional Certifications; Table 13. Thread Adapter Thread Sizes
Quick Start Guide 23 February 2015 Special Conditions for Safe Use (X): 1. When the thread adapter is used with an enclosure in type of protection increased safety “e” the entry thread shall be suitably sealed in order to maintain the ingress protection rating (IP) of the enclosure. 2. The blanking ...
Page 24 - Figure 11. Rosemount 3051 EC Declaration of Conformity
February 2015 24 Quick Start Guide Figure 11. Rosemount 3051 EC Declaration of Conformity