2 Wiring Diagram A diagram noting all components and their proper wiring isprovided. (See Fig. 11) Installation Report An Installation Report is provided at the end of this document, where you should record installation notes for each Gateway(Coordinator), and issues encountered. Recommended Order o...
Page 3 - INSTALLATION; Basic list of tools and materials recommended to; Relay; Suggested Installation Sequence; WARNING; Mount Modem Enclosure:; CAUTION
3 INSTALLATION Basic list of tools and materials recommended to complete installation: Material S Small blue wire nuts S 9/16--in. Rubber grommet S #18 THHN standard wire S #18--22 fork connectors S #18--22 female connectors S #10 tek screws (3/4--in. long) S 5--1/2--in. And 7--1/2--in. zip ties S T...
Page 4 - Coordinator; Mount Transformer; Securely mount the transformer using 4 of the supplied mounting; Transformer; Ensure the locking tabs are fully secured.; Connect Data Cables; Attach the 3--wire Molex connector from the Modem Enclosure to; Install Antenna and Mounting Base; ACCESSORY RELIABILITY HAZARD; Failure to follow this caution may result in accessory
4 Coordinator C13335 Fig. 4 -- Gateway (Coordinator) Mounting Examples Mount Transformer Securely mount the transformer using 4 of the supplied mounting screws. (See Fig. 5) Secondary Side, 24V Primary Side C13336 Fig. 5 -- Transformer Mount 4--Pole Relay S Securely mount the 4--pole relay using the...
Page 5 - Legs of Load-Side Leads; CTs; Controller Molex; Connect Power Lines; NOTE
5 2 Legs of Load-Side Leads CTs CT secured around the load-side leads Locking Tab CT Molex Connectormated to one of the Controller Molex Connectors C13338 Fig. 9 -- Connecting Current Sensors Connect Power Lines 1. Connect the following wires in parallel to the 24V side of the transformer: a. Modem ...
Page 6 - Do not proceed to the next step until the Relay Test completes; Test Gateway (Coordinator) Signal Strength; GATEWAY; Controls
6 automatically exits the Relay Test Mode and commences regularoperation.After finished the relay test, leave the jumpers connected for at least five more minutes in order to capture the readings for the maximum load of the unit. Do not proceed to the next step until the Relay Test completes success...
Page 7 - Parts List; below
7 Parts List The following equipment is shipped with each Gateway(Coordinator) Accessory. 1. Gateway (Coordinator) Controller2. Magnetic antenna base3. Antenna 4. Modem enclosure (with modem inside)5. (2) Current Transformers6. 4--Pole Relay (pre--wired with extension wires)7. Mounting screws (suppl...
Page 8 - Site Installation Report
8 Site Installation Report Section 1.- Site SummaryCustomer Name Site Address Customer Phone Number Customer Email Installation Contractor Section 2.- Installation DetailsQty. of Modems/Gateways (Coordinators) Shipped Installed Qty. of Load Controllers Shipped Installed Qty. of 4-Pole Relays Shipped...
Page 9 - Blower Delay; stage Delay; Power up RTU & confirm controller connects to net-; (Confirm READY indicator and at least two
9 Gateway (Coordinator) RTU Checklist Gateway (Coordinator) Installation Checklist Site RTU #, Zone Name Controller ID Today’s Date Installer Name REGEN Energy Operations Center/Support- (949) 258-4415, Option #2 Step Notes 1 Power off RTU 2 Install Gateway (Coordinator) and components, incl. wiri...